C_ACTIVATE12 · Question #47
C_ACTIVATE12 Question #47: Real Exam Question with Answer & Explanation
The correct answer is B. To perform sprint testing. See the full explanation below for the reasoning.
Question
What is the purpose of a firm-up sprint? Please choose the correct answer. Response:
Options
- ATo demonstrate functionality from previous sprint
- BTo perform sprint testing
- CTo revise a release plan and sprint plan
- DTo run end-to-end integration test