C_ACTIVATE12 · Question #40

Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase? Please choose the correct answer…

The correct answer is D. Conduct Delta Design workshops. See the full explanation below for the reasoning.

Question

Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase? Please choose the correct answer. Response:

Options

  • Aa) Conduct Solution Validation workshops
  • BConduct Solution Validation workshops
  • CPrioritize initial backlog
  • DConduct Delta Design workshops

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    10% (4)
  • C
    12% (5)
  • D
    76% (32)