The correct answer is D. Conduct Delta Design workshops. See the full explanation below for the reasoning.

Question

Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase? Please choose the correct answer. Response:

Options

  • Aa) Conduct Solution Validation workshops
  • BConduct Solution Validation workshops
  • CPrioritize initial backlog
  • DConduct Delta Design workshops