When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer. Response:
The correct answer is C. During the sprint review. See the full explanation below for the reasoning.
Question
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer. Response:
Options
- ADuring the daily SCRUM meeting
- BDuring the sprint retrospective
- CDuring the sprint review
- DDuring user acceptance testing
How the community answered
(15 responses)- A7% (1)
- B13% (2)
- C73% (11)
- D7% (1)