C_ACTIVATE12 · Question #186

Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? There are 3 correct answers to this question.

The correct answer is C. Creating transnational data D. Changing master data E. Organizational structure. See the full explanation below for the reasoning.

Question

Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? There are 3 correct answers to this question.

Options

  • AAdjusting custom code objects
  • BImplementing best practices
  • CCreating transnational data
  • DChanging master data
  • EOrganizational structure

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    16% (6)
  • C
    79% (30)