What is the basis for approving work results (signing act of acceptance) on a project phase level?
The correct answer is D. Agreed and met acceptance criteria within quality gate. See the full explanation below for the reasoning.
Question
What is the basis for approving work results (signing act of acceptance) on a project phase level?
Options
- ADefinition of done for user story
- BScrum of scrums meeting decision
- CDefinition of ready for sprint
- DAgreed and met acceptance criteria within quality gate
How the community answered
(45 responses)- A4% (2)
- B9% (4)
- C2% (1)
- D84% (38)