C_ACTIVATE12 · Question #17
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer. Response:
The correct answer is D. Deploy. See the full explanation below for the reasoning.
Question
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer. Response:
Options
- APrepare
- BExplore
- CRealize
- DDeploy
How the community answered
(44 responses)- A2% (1)
- B7% (3)
- C14% (6)
- D77% (34)