Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question

The correct answer is B. Conduct Scope Validation D. Perform Fit/Gap Analysis. See the full explanation below for the reasoning.

Question

Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question

Options

  • ASchedule kick-off workshop
  • BConduct Scope Validation
  • CConfirm Integration prerequisites
  • DPerform Fit/Gap Analysis

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    74% (17)
  • C
    17% (4)