Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the correct answer. Response:
The correct answer is D. Product Owner's relative estimate of the effort that will be needed to implement the user story. See the full explanation below for the reasoning.
Question
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the correct answer. Response:
Options
- ADetailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
- BRelative estimate in ideal person days that reflects the best estimate provided by the project team
- CDetailed bottom-up effort estimate by the SCRUM Master in story points based on the user story
- DProduct Owner's relative estimate of the effort that will be needed to implement the user story
How the community answered
(36 responses)- A14% (5)
- B6% (2)
- C3% (1)
- D78% (28)