What is the correct order of the SAP Activate Methodology phases?

The correct answer is D. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run. See the full explanation below for the reasoning.

Question

What is the correct order of the SAP Activate Methodology phases?

Options

  • APrepare -> Discover -> Explore -> Realize -> Deploy -> Run
  • BPlan -> Design -> Build -> Operate
  • CPlan -> Build -> Run -> Sustain
  • DDiscover -> Prepare -> Explore -> Realize -> Deploy -> Run

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    11% (3)
  • D
    81% (22)