SAP
C_ACTIVATE12 · Question #140
What is the correct order of the SAP Activate Methodology phases?
The correct answer is D. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run. See the full explanation below for the reasoning.
Question
What is the correct order of the SAP Activate Methodology phases?
Options
- APrepare -> Discover -> Explore -> Realize -> Deploy -> Run
- BPlan -> Design -> Build -> Operate
- CPlan -> Build -> Run -> Sustain
- DDiscover -> Prepare -> Explore -> Realize -> Deploy -> Run
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C11% (3)
- D81% (22)
Community Discussion
No community discussion yet for this question.