How are the build and test tasks planned and executed in the Realize phase? Please choose the correct answer. Response:
Options
- ABy using the sprint backlog list as input for each iteration.
- BBy executing regression tests after each iteration
- CWith Q-Gates for sign off after each iteration
- DBy using incremental build in fixed-scope iteration