SAP
C_ACTIVATE12 · Question #132
How are the build and test tasks planned and executed in the Realize phase? Please choose the correct answer. Response:
The correct answer is D. By using incremental build in fixed-scope iteration. See the full explanation below for the reasoning.
Question
How are the build and test tasks planned and executed in the Realize phase? Please choose the correct answer. Response:
Options
- ABy using the sprint backlog list as input for each iteration.
- BBy executing regression tests after each iteration
- CWith Q-Gates for sign off after each iteration
- DBy using incremental build in fixed-scope iteration
How the community answered
(58 responses)- A9% (5)
- B3% (2)
- C17% (10)
- D71% (41)
Community Discussion
No community discussion yet for this question.