SAP
C_ACTIVATE12 · Question #117
Which of the following is not correct about workstreams? There are 2 correct answers to this question.
The correct answer is A. It is assigned as attribute to phases, deliverables and tasks. D. Workstreams are dependent on phase start and end. See the full explanation below for the reasoning.
Question
Which of the following is not correct about workstreams? There are 2 correct answers to this question.
Options
- AIt is assigned as attribute to phases, deliverables and tasks.
- BIt can span phases
- CIt is a collection of related deliverables
- DWorkstreams are dependent on phase start and end
How the community answered
(25 responses)- A84% (21)
- B12% (3)
- C4% (1)