C_ACTIVATE12 · Question #114
What does a project jump-start include for a new implementation of SAP S/4HANA on- premise edition? Please choose the correct answer. Response:
The correct answer is A. SAP Best Practices. See the full explanation below for the reasoning.
Question
What does a project jump-start include for a new implementation of SAP S/4HANA on- premise edition? Please choose the correct answer. Response:
Options
- ASAP Best Practices
- BRapid prototyping
- CProject team training
- DFull project SCRUM
How the community answered
(19 responses)- A74% (14)
- B16% (3)
- C5% (1)
- D5% (1)