C_A1FIN_10 · Question #76

Which "additional" planning method is available for internal orders if you have information about sources of supply and vendors' prices based on quantities?

The correct answer is A. Unit cost planning. See the full explanation below for the reasoning.

Question

Which "additional" planning method is available for internal orders if you have information about sources of supply and vendors' prices based on quantities?

Options

  • AUnit cost planning
  • BActivity input planning
  • COverall planning
  • DPrimary cost planning

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    4% (1)
  • C
    15% (4)
  • D
    8% (2)