C_A1FIN_10 · Question #72
During the preparation phase, you create a project charter and define project standards and procedures. These elements give the project manager the authority to conduct a project within scope…
The correct answer is D. Document scope change requests according to the change requests plan and decide on. See the full explanation below for the reasoning.
Question
During the preparation phase, you create a project charter and define project standards and procedures. These elements give the project manager the authority to conduct a project within scope, quality, time, and cost and resource constraints. Which approach would you recommend for scope change requests?
Options
- ASince the project is a fixed scope project, reject all scope change requests.
- BOnly accept scope change requests after integration and acceptance tests.
- CCollect scope change requests and hand them over to development immediately.
- DDocument scope change requests according to the change requests plan and decide on
How the community answered
(25 responses)- A8% (2)
- B12% (3)
- D80% (20)