SAP
C_A1FIN_10 · Question #64
Which of the following tasks should be executed prior to the official start of implementation? (Choose three)
The correct answer is A. Map and extract data D. Review predefined roles and assign users E. Cleanse legacy data. See the full explanation below for the reasoning.
Question
Which of the following tasks should be executed prior to the official start of implementation? (Choose three)
Options
- AMap and extract data
- BAdapt forms and reports
- CFine tune the organizational structure configuration
- DReview predefined roles and assign users
- ECleanse legacy data
How the community answered
(48 responses)- A71% (34)
- B19% (9)
- C10% (5)
Community Discussion