Before you start validating the solution with the key users in the realization phase of an SAP ERP- based Business All-in-One project, which systems must be up and running?
The correct answer is B. The development system with SAP ERP and the Best Practices add-ons installed. See the full explanation below for the reasoning.
Question
Before you start validating the solution with the key users in the realization phase of an SAP ERP- based Business All-in-One project, which systems must be up and running?
Options
- AAll systems used in the implementation must be up and running
- BThe development system with SAP ERP and the Best Practices add-ons installed
- CThe productive system with SAP ERP, the Best Practices add-ons, and Solution Manager
- DThe development and quality systems with SAP ERP and the Best Practices add-ons installed
How the community answered
(48 responses)- A10% (5)
- B79% (38)
- C6% (3)
- D4% (2)