C_A1FIN_10 · Question #43
You have finished the integration test and are about to migrate to the production environment. One of the tasks of the cutover process is to transfer the Customizing from the development environment…
The correct answer is B. Company codes, controlling areas, plants, and charts of accounts. See the full explanation below for the reasoning.
Question
You have finished the integration test and are about to migrate to the production environment. One of the tasks of the cutover process is to transfer the Customizing from the development environment to the production environment using transport requests. What will be transferred to the production environment via transport requests?
Options
- ACompany codes, controlling areas, plants, charts of accounts, and cost centers
- BCompany codes, controlling areas, plants, and charts of accounts
- CCompany codes, controlling areas, plants, charts of accounts, cost centers, and internal orders
- DCompany codes, controlling areas, plants, charts of accounts, and internal orders
How the community answered
(26 responses)- A12% (3)
- B81% (21)
- C4% (1)
- D4% (1)