What is created when a primary cost is posted to a cost center?
The correct answer is D. A CO document that contains the cost center, the cost element, and the amount. See the full explanation below for the reasoning.
Question
What is created when a primary cost is posted to a cost center?
Options
- AA CO document that contains the cost center, the sending PandL account, and the amount
- BA journal entry that credits the sending object and debits the receiving CO object
- CA journal entry that debits the sending object and credits the receiving CO object
- DA CO document that contains the cost center, the cost element, and the amount
How the community answered
(49 responses)- A8% (4)
- B14% (7)
- C4% (2)
- D73% (36)