C_A1FIN_10 · Question #27

What master data do we use to allocate costs, based on quantities, valuated by a price?

The correct answer is A. Activity types. See the full explanation below for the reasoning.

Question

What master data do we use to allocate costs, based on quantities, valuated by a price?

Options

  • AActivity types
  • BPrimary cost elements
  • CCost centers
  • DInternal orders

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    4% (1)
  • C
    15% (4)
  • D
    4% (1)