C_A1FIN_10 · Question #27
What master data do we use to allocate costs, based on quantities, valuated by a price?
The correct answer is A. Activity types. See the full explanation below for the reasoning.
Question
What master data do we use to allocate costs, based on quantities, valuated by a price?
Options
- AActivity types
- BPrimary cost elements
- CCost centers
- DInternal orders
How the community answered
(26 responses)- A77% (20)
- B4% (1)
- C15% (4)
- D4% (1)