Which task must be completed before using the Job Manager?
The correct answer is D. Create a Job Manager profile and a profile for each target node that needs to be managed. See the full explanation below for the reasoning.
Question
Which task must be completed before using the Job Manager?
Options
- ACreate an administrative agent for all the nodes in the cell.
- BEnsure that the profiles in the environment all have security enabled
- CFederate any stand-alone nodes to the deployment manager in the cell.
- DCreate a Job Manager profile and a profile for each target node that needs to be managed.
How the community answered
(26 responses)- A4% (1)
- B15% (4)
- C8% (2)
- D73% (19)