A customer wants to implement a 3-site continuous copy solution with three D38800 systems. A three-site Business Continuity (BC) license and TotalStorage Productively Center for Replication (TPC-R)…
The correct answer is D. Ensure paths exists between the 3 DS8800 systems. See the full explanation below for the reasoning.
Question
A customer wants to implement a 3-site continuous copy solution with three D38800 systems. A three-site Business Continuity (BC) license and TotalStorage Productively Center for Replication (TPC-R) are already installed. Which action should be completed before using the TPC-R GUI to configure the Metro/Global Mirror?
Options
- ASelect the action Start H1-'H2->H3
- BConfigure the CIMON agent on the DSS800
- CAdd copy sets to the Metro/Global Mirror session
- DEnsure paths exists between the 3 DS8800 systems
How the community answered
(34 responses)- A12% (4)
- B3% (1)
- C6% (2)
- D79% (27)
Community Discussion
No community discussion yet for this question.