A customer wants a comparison of a public cloud subscription-based solution versus an in- house solution for a new project. The customer has requested a TOO for each solution using a four year…
The correct answer is D. Expected increase of users over the project lifetime. See the full explanation below for the reasoning.
Question
A customer wants a comparison of a public cloud subscription-based solution versus an in- house solution for a new project. The customer has requested a TOO for each solution using a four year solution life cycle. Which of the following factors should be included as part of the public cloud solution's TOO?
Options
- ACost per kilowatt hour
- BInstallation expenses of new hardware
- CCost of new server operating system licenses
- DExpected increase of users over the project lifetime
How the community answered
(21 responses)- A10% (2)
- B5% (1)
- C5% (1)
- D81% (17)