When converting an existing Global Mirror relationship to a Metro Mirror relationship how can the initial data synchronization be avoided'?

The correct answer is D. Specify that the master and auxiliary volumes contain the same data. See the full explanation below for the reasoning.

Question

When converting an existing Global Mirror relationship to a Metro Mirror relationship how can the initial data synchronization be avoided'?

Options

  • ACreate a Volume Mirror of the master volume
  • BSpecify FlashCopy targets as master and auxiliary volumes
  • CCreate a FlashCopy with "Clone" preset of the master volume
  • DSpecify that the master and auxiliary volumes contain the same data

How the community answered

(31 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    6% (2)
  • D
    77% (24)