nerdexam
IBM

C4090-451 · Question #70

A prospect is considering a single chassis PureFlex. Which of the following business pressures could be reduced with the installation of PureFlex?

The correct answer is B. Deploying applications faster for quicker time to market. See the full explanation below for the reasoning.

Question

A prospect is considering a single chassis PureFlex. Which of the following business pressures could be reduced with the installation of PureFlex?

Options

  • AEmploying more cost effective open products
  • BDeploying applications faster for quicker time to market
  • CReduce cost management of zBX, System x, and Power servers
  • DTop-of-rack (TOR) switches flattens the network to reduce management costs

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    76% (16)
  • C
    5% (1)
  • D
    14% (3)

Community Discussion

No community discussion yet for this question.