To prevent data loss, what should be a part of a migration plan prior to starting the migration of production data'?

The correct answer is D. Ensure the customer has a tested and working backup and restore procedure. See the full explanation below for the reasoning.

Question

To prevent data loss, what should be a part of a migration plan prior to starting the migration of production data'?

Options

  • AA proven database "roll-back" procedure
  • BTotal number of arrays mapped to the customer's hosts
  • CThe customer's current RAID level and number of drives
  • DEnsure the customer has a tested and working backup and restore procedure

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    11% (4)
  • D
    81% (30)