IBM
C4090-451 · Question #21
To prevent data loss, what should be a part of a migration plan prior to starting the migration of production data'?
The correct answer is D. Ensure the customer has a tested and working backup and restore procedure. See the full explanation below for the reasoning.
Question
To prevent data loss, what should be a part of a migration plan prior to starting the migration of production data'?
Options
- AA proven database "roll-back" procedure
- BTotal number of arrays mapped to the customer's hosts
- CThe customer's current RAID level and number of drives
- DEnsure the customer has a tested and working backup and restore procedure
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C11% (4)
- D81% (30)
Community Discussion
No community discussion yet for this question.