A customer is planning an upgrade to their System z servers. The CFO wants to compare the anticipated net improvement of the bottom line with the amount invested in the project. Which of the…
The correct answer is C. Return on investment. See the full explanation below for the reasoning.
Question
A customer is planning an upgrade to their System z servers. The CFO wants to compare the anticipated net improvement of the bottom line with the amount invested in the project. Which of the following is the common name for this financial comparison?
Options
- AAcid test ratio
- BPayback period
- CReturn on investment
- DReturn on capital
How the community answered
(30 responses)- A17% (5)
- B7% (2)
- C70% (21)
- D7% (2)
Community Discussion