A customer is planning an upgrade to a z114. They have indicated that they will be adding additional disk storage in the future and want to make sure they have room for non disruptive future I/O…

The correct answer is C. Carefully plan out the upgrade based upon the current I/O configuration. Confirm there is enough. See the full explanation below for the reasoning.

Question

A customer is planning an upgrade to a z114. They have indicated that they will be adding additional disk storage in the future and want to make sure they have room for non disruptive future I/O growth. Which of the following is the appropriate first action for the Technical Specialist?

Options

  • AUse the eConfig Plan Ahead feature to place an order for an additional I/O drawer but don order
  • BAsk the sales specialist to give the customer a discount and order the cards at the end of the
  • CCarefully plan out the upgrade based upon the current I/O configuration. Confirm there is enough
  • DThe z114 hardware model M10 has more I/O adapters so you should order the M10 model which

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    85% (39)
  • D
    9% (4)