nerdexam
IBM

C4070-604 · Question #40

In a pre-Sale TDA review meeting, what requirement below is recommended before placing an order for new or upgrade system z114 or z196 machine being proposed. Which of the following requirements…

The correct answer is C. Capacity Planning Analysis. See the full explanation below for the reasoning.

Question

In a pre-Sale TDA review meeting, what requirement below is recommended before placing an order for new or upgrade system z114 or z196 machine being proposed. Which of the following requirements must be performed before the TDA review?

Options

  • ASW Configuration
  • BContract Proposal
  • CCapacity Planning Analysis
  • DProject Plan

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    77% (30)
  • D
    13% (5)

Community Discussion

No community discussion yet for this question.

Full C4070-604 Practice