The correct answer is B. There is Plan Ahead option available for the I/O drawers. See the full explanation below for the reasoning.
Question
A customer technical staff has been briefed on migration to a z114 or z196. They are discussing the new features with the System z Technical Specialist. Which of the following customer statements is incorrect and must be corrected by the Technical Specialist?
Options
- AAddition and removal of z196 I/O cage is disruptive
- BThere is Plan Ahead option available for the I/O drawers
- CThe I/O drawers can be added or removed non-disruptively
- DThe correct mix of I/O cage and drawers is configured based on the number and type of I/O
Community Discussion