A System z customer technical staff is planning to upgrade their z9 to a new z114 with a Migration Offering. The customer group is discussing their plan with the System z technical specialist. Which…
The correct answer is C. For a Migration Offering upgrade the existing mainframe and parts must be returned to IBM within. See the full explanation below for the reasoning.
Question
A System z customer technical staff is planning to upgrade their z9 to a new z114 with a Migration Offering. The customer group is discussing their plan with the System z technical specialist. Which of the following customer statements is in error and must be corrected by the technical specialist?
Options
- AThe plan must include an accurate measurement of the z114 performance and capacity.
- BThe post installation plan should consider that the z114 might have to be taken out of service for
- CFor a Migration Offering upgrade the existing mainframe and parts must be returned to IBM within
- DThe post installation plan should include disaster recovery considerations including emergency
How the community answered
(21 responses)- B10% (2)
- C86% (18)
- D5% (1)
Community Discussion