A customer is migrating to z114 and z/VM V6.1. The existing z9 BC will be used as cold standby system in a separate datacenter. Which of the following is correct?

The correct answer is B. The latest version of z/VM supported on z9 BC is z/VM V5.4. However the guests stay. See the full explanation below for the reasoning.

Question

A customer is migrating to z114 and z/VM V6.1. The existing z9 BC will be used as cold standby system in a separate datacenter. Which of the following is correct?

Options

  • AIn order to run all guests on the z9 BC both, z9 BC and z114, have to run z/VM V6.1
  • BThe latest version of z/VM supported on z9 BC is z/VM V5.4. However the guests stay
  • CIn order to keep z/VM guests both systems (z114 & z9 BC) need to run z/VM V5.4.
  • DThe customer has to run z/VM V6.1 as a second level guest on the z9 BC z/VM V5.4The

How the community answered

(51 responses)
  • A
    8% (4)
  • B
    71% (36)
  • C
    18% (9)
  • D
    4% (2)