nerdexam
IBM

C4040-227 · Question #214

With regard to planned maintenance, which statement about interim fix management is correct?

The correct answer is D. If the updates include the official APAR, the update_all process will automatically uninstall the interim fix. See the full explanation below for the reasoning.

Question

With regard to planned maintenance, which statement about interim fix management is correct?

Options

  • AThe interim fix must be manually committed prior to applying the updates.
  • BThe interim fix will be automatically committed as part of the update process.
  • CIf the fileset associated with interim fix will not be updated, it still needs to be temporarily rejected.
  • DIf the updates include the official APAR, the update_all process will automatically uninstall the interim fix

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    10% (5)
  • D
    83% (40)

Community Discussion

No community discussion yet for this question.

Full C4040-227 Practice