With regard to planned maintenance, which statement about interim fix management is correct?
The correct answer is D. If the updates include the official APAR, the update_all process will automatically uninstall the interim fix. See the full explanation below for the reasoning.
Question
With regard to planned maintenance, which statement about interim fix management is correct?
Options
- AThe interim fix must be manually committed prior to applying the updates.
- BThe interim fix will be automatically committed as part of the update process.
- CIf the fileset associated with interim fix will not be updated, it still needs to be temporarily rejected.
- DIf the updates include the official APAR, the update_all process will automatically uninstall the interim fix
How the community answered
(48 responses)- A2% (1)
- B4% (2)
- C10% (5)
- D83% (40)
Community Discussion