A customer has a production 16-core POWER7+ 770 with 8 cores currently active. They are considering purchasing a POWER7÷ 770 Capacity Back Up (CBU) with the same processing capacity. What must be…

The correct answer is C. The CBU feature, (8) core activations and a minimum of (1) processor entitlements of IBM i. See the full explanation below for the reasoning.

Question

A customer has a production 16-core POWER7+ 770 with 8 cores currently active. They are considering purchasing a POWER7÷ 770 Capacity Back Up (CBU) with the same processing capacity. What must be included in the new POWER7+ 770 CBU configuration?

Options

  • AThe CBU feature, (8) core activations and (8) processor entitlements of IBM i
  • BThe CBU feature, no core activations and a minimum of (1) processor entitlement of IBM i
  • CThe CBU feature, (8) core activations and a minimum of (1) processor entitlements of IBM i
  • DThe CBU feature, no core activations, (1) processor entitlements of IBM i and (1) Enterprise

How the community answered

(21 responses)
  • A
    14% (3)
  • B
    10% (2)
  • C
    71% (15)
  • D
    5% (1)