C4040-225 · Question #86
A customer has a mix of POWER5, POWER6, and POWER7 systems and wants to measure and control the power utilization. What is needed to support this requirement?
The correct answer is A. Intelligent PDU (iPDU). See the full explanation below for the reasoning.
Question
A customer has a mix of POWER5, POWER6, and POWER7 systems and wants to measure and control the power utilization. What is needed to support this requirement?
Options
- AIntelligent PDU (iPDU)
- BIntelligent PDU (iPDU)
- CEnergy Star rating
- DActive Energy Manager
How the community answered
(29 responses)- A72% (21)
- B3% (1)
- C10% (3)
- D14% (4)