A customer is considering adding more workloads to their production 6-core Power 720. The server already has several IBM i LPARs with dedicated resources. What information would help the technical…
The correct answer is A. A current system plan. See the full explanation below for the reasoning.
Question
A customer is considering adding more workloads to their production 6-core Power 720. The server already has several IBM i LPARs with dedicated resources. What information would help the technical representative determine the upgrade configuration needed?
Options
- AA current system plan
- BAn ASMI hardware report
- CA system configuration list generated from the HMC
How the community answered
(23 responses)- A74% (17)
- B9% (2)
- C17% (4)