When preparing to install a System WPAR using NIM, what action must occur before the planned WPAR can be successfully defined as a NIM client?
The correct answer is C. Define the global environment LPAR as a NIM client. See the full explanation below for the reasoning.
Question
When preparing to install a System WPAR using NIM, what action must occur before the planned WPAR can be successfully defined as a NIM client?
Options
- AInstall AIX onto the global environment.
- BRegister the planned hostnames to DNS.
- CDefine the global environment LPAR as a NIM client.
- DCreate an lpp_source with the WPAR-specific backup files.
How the community answered
(34 responses)- A3% (1)
- B12% (4)
- C76% (26)
- D9% (3)