IBM
C4040-123 · Question #80
A company is purchasing a new Power Systems server and plans to support several AIX partitions. They are unsure about their total memory requirements. Which of the following describes a resource…
The correct answer is D. Active Memory Sharing avoids having to assign a dedicated amount of physical memory to. See the full explanation below for the reasoning.
Question
A company is purchasing a new Power Systems server and plans to support several AIX partitions. They are unsure about their total memory requirements. Which of the following describes a resource management technology that can be used to provide maximum memory utilization and flexibility?
Options
- AThe HMC can be scheduled to dynamically reallocate memory resources among the partitions.
- BLogical Volume Manager allows the system administrator to reconfigure the memoryresources
- CActive Memory Deduplication permits the allocation of memory resources to be dynamically
- DActive Memory Sharing avoids having to assign a dedicated amount of physical memory to
How the community answered
(40 responses)- A18% (7)
- B5% (2)
- C8% (3)
- D70% (28)