An AIX customer who has a POWER6 570 with PowerVM Enterprise Edition plans to upgrade to a POWER7+ 770. Applications moving from the POWER6 570 to the POWER7+ 770 must remain available. Which option…

The correct answer is B. Install the POWER7+ 770 and use Live Partition Mobility to move the applications from the. See the full explanation below for the reasoning.

Question

An AIX customer who has a POWER6 570 with PowerVM Enterprise Edition plans to upgrade to a POWER7+ 770. Applications moving from the POWER6 570 to the POWER7+ 770 must remain available. Which option will support minimal outage to the application environment?

Options

  • AInstall Smart Cloud Entry on the POWER7+ 770 and use the integrated migration tool to move the
  • BInstall the POWER7+ 770 and use Live Partition Mobility to move the applications from the
  • CInstall PowerHA System Mirror on both the POWER6 570 and the POWER7+ 770 and do a
  • DPerform a disk copy on the POWER6 570 and restore the image on the POWER7+ 770.

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    80% (39)
  • C
    10% (5)
  • D
    6% (3)