What solution can be deployed to enable maintenance on a server while ensuring that a mission critical LPAR remains operational?

The correct answer is B. Use PowerVM Enterprise Edition to move the partition to another server. See the full explanation below for the reasoning.

Question

What solution can be deployed to enable maintenance on a server while ensuring that a mission critical LPAR remains operational?

Options

  • AUse PowerSC to insure continuous uptime on another server.
  • BUse PowerVM Enterprise Edition to move the partition to another server.
  • CUse Active Memory Sharing to enable the LPAR to continue running on the current server
  • DUse VMControl Enterprise Edition to suspend and resume the application on the current server.

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    79% (38)
  • C
    13% (6)
  • D
    2% (1)