IBM
C4040-108 · Question #48
A customer is planning to convert vacant office space to a data center that will be populated with several standard Power 795 systems. During a pre-delivery site inspection, the customer is told by…
The correct answer is A. The computer room does not have the required raised floor. See the full explanation below for the reasoning.
Question
A customer is planning to convert vacant office space to a data center that will be populated with several standard Power 795 systems. During a pre-delivery site inspection, the customer is told by the Installation Planning Representative that the data center is inadequately equipped to receive the systems. Which of the following situations will prevent proper installation?
Options
- AThe computer room does not have the required raised floor.
- BThe computer room does not have the required overhead cable racks.
- CThe computer room does not have the required emergency power off switch.
- DThe computer room does not have the required uninterruptable power supply infrastructure.
How the community answered
(35 responses)- A77% (27)
- B9% (3)
- C3% (1)
- D11% (4)
Community Discussion
No community discussion yet for this question.