Customer wants to consolidate POWER4, POWER5 and POWER6 systems on to a POWER7 server. What resource will indicate an appropriate POWER7 server?

The correct answer is A. Power Systems Performance Report. See the full explanation below for the reasoning.

Question

Customer wants to consolidate POWER4, POWER5 and POWER6 systems on to a POWER7 server. What resource will indicate an appropriate POWER7 server?

Options

  • APower Systems Performance Report
  • BPower System Consolidation Handbook
  • CPower Systems Hardware Information Center
  • DPower Systems HardwareServer Specification sheet

How the community answered

(39 responses)
  • A
    74% (29)
  • B
    15% (6)
  • C
    5% (2)
  • D
    5% (2)

Community Discussion

No community discussion yet for this question.

Full C4040-108 Practice