nerdexam
IBM

C2180-404 · Question #28

A solution developer wants to monitor how much Java processing memory is currently allocated to an integration server. A flow is currently deployed. Assuming resource statistics collection has been…

The correct answer is B. Expand Integration Nodes folder in IBM Integration Explorer Choose Window menu: Show view. See the full explanation below for the reasoning.

Question

A solution developer wants to monitor how much Java processing memory is currently allocated to an integration server. A flow is currently deployed. Assuming resource statistics collection has been started, which step will allow the developer to obtain these statistics?

Options

  • AExpand Integration Nodes folder in IBM Integration Explorer Choose Window menu: Show view:
  • BExpand Integration Nodes folder in IBM Integration Explorer Choose Window menu: Show view:
  • CExpand Integration Nodes in IBM Integration Toolkit Choose Window menu: Show view: Resource
  • DExpand Integration Nodes in IBM Integration Toolkit Choose Window menu: Show view: Resource

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    81% (29)
  • C
    3% (1)
  • D
    11% (4)

Community Discussion

No community discussion yet for this question.

Full C2180-404 Practice