A solution implementer needs to immediately quiesce a DataPower appliance in the event of a power supply failure. How can the solution implementer satisfy this requirement?

The correct answer is B. Configure an Event Trigger for the power supply failure event to execute the "appliance- "quiesce". See the full explanation below for the reasoning.

Question

A solution implementer needs to immediately quiesce a DataPower appliance in the event of a power supply failure. How can the solution implementer satisfy this requirement?

Options

  • AConfigure an Event Filter for the power supply failure event to execute the "appliance-quiesce"
  • BConfigure an Event Trigger for the power supply failure event to execute the "appliance- "quiesce"
  • CConfigure an Event Subscription for the power supply failure event to execute the "appliance-
  • DCreate a Scheduled Processing Rule that parses the system log to execute the SOMA request to

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    82% (27)
  • C
    3% (1)
  • D
    9% (3)