Question
A company has a large network of WebSphere MQ clustered queue managers that span multiple applications. When migrating such a cluster to a new version, which one of the following is a good practice?
Options
- APerform a staged migration, in which queue managers are migrated one at a time.
- BStage the migration, but migrate all the queue managers on a particular operating system
- CAt a minimum, migrate the full repositories at the same time, to avoid incompatibilities in
- DMigrate all the queue managers in the cluster at the same time to make sure there are