The correct answer is D. There is a new maximum instance channel limit that can catch a client application. See the full explanation below for the reasoning.
Question
A company needs to improve availability of client connections for its distributed applications. Which one of the following is a true statement about a new option or capability of WebSphere MQV7.0 that could improve availability?
Options
- ATCP/IP client connections are now always full duplex, and full duplex can support
- BClient connections on the same server can share an instance of a channel connection,
- CThe new MQSTAT verb can be used to determine the health of a Queue Manager, leading
- DThere is a new maximum instance channel limit that can catch a client application