A broker is experiencing an abend with an execution group. The issue occurs intermittently but causes downtime. The administrator needs to open a Problem Management Report (PMR). What is the correct…
The correct answer is B. 2. See the full explanation below for the reasoning.
Question
A broker is experiencing an abend with an execution group. The issue occurs intermittently but causes downtime. The administrator needs to open a Problem Management Report (PMR). What is the correct severity?
Options
- A1
- B2
- C3
- D4
How the community answered
(26 responses)- A12% (3)
- B77% (20)
- C8% (2)
- D4% (1)