A solution implementer needs to immediately quiesce a DataPower appliance in the event of a power supply failure. How can the solution implementer satisfy this requirement?
The correct answer is B. Configure an Event Trigger for the power supply failure event to execute the "appliance-quiesce". See the full explanation below for the reasoning.
Question
A solution implementer needs to immediately quiesce a DataPower appliance in the event of a power supply failure. How can the solution implementer satisfy this requirement?
Options
- AConfigure an Event Filter for the power supply failure event to execute the "appliance-quiesce"
- BConfigure an Event Trigger for the power supply failure event to execute the "appliance-quiesce"
- CConfigure an Event Subscription for the power supply failure event to execute the "appliance-
- DCreate a Scheduled Processing Rule that parses the system log to execute the SOMA request to
How the community answered
(29 responses)- A3% (1)
- B83% (24)
- C10% (3)
- D3% (1)