Given an existing TestManager Rational Test project, what are the steps to log results to TestManager?

The correct answer is C. from RFT, associate the Rational Test Project with the RFT project, then select the. See the full explanation below for the reasoning.

Question

Given an existing TestManager Rational Test project, what are the steps to log results to TestManager?

Options

  • Afrom TestManager, create a new Test Script Type for RFT, then from RFT, select the Functional
  • Bfrom RFT, select the Functional Test logging preferences to TestManager, then select
  • Cfrom RFT, associate the Rational Test Project with the RFT project, then select the
  • Dfrom the Rational Administrator, associate the RFT project to the Rational Test Project, thenfrom

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    5% (1)
  • C
    70% (14)
  • D
    15% (3)