C2140-820 · Question #7

C2140-820 Question #7: Real Exam Question with Answer & Explanation

The correct answer is C. the average number of story points the team can deliver in an iteration. See the full explanation below for the reasoning.

Question

What is the velocity for a development team following the Scrum process template?

Options

  • Athe average number of hours the team can deliver in an iteration
  • Bthe average number of stories the team can deliver in an iteration
  • Cthe average number of story points the team can deliver in an iteration
  • Dthe average number of tasks the team can deliver in an iteration