A project manager is creating a new plan view and does not like the default display. What are the other plan view display options?
The correct answer is D. Tree, Taskboard, and Kanban. See the full explanation below for the reasoning.
Question
A project manager is creating a new plan view and does not like the default display. What are the other plan view display options?
Options
- AWork Breakdown, Taskboard, and Roadmap
- BLoad, Progress (Hours), and Progress (Size)
- CTree, Bars, and Folder
- DTree, Taskboard, and Kanban
How the community answered
(16 responses)- A19% (3)
- B6% (1)
- D75% (12)
Community Discussion