Question

A project manager is creating a new plan view and does not like the default display. What are the other plan view display options?

Options

  • AWork Breakdown, Taskboard, and Roadmap
  • BLoad, Progress (Hours), and Progress (Size)
  • CTree, Bars, and Folder
  • DTree, Taskboard, and Kanban